Monday, 13 October 2014

Slam Dunk Footing Report for Primary School Basketball Rings!

Bridgewater Primary School recently had two basketball rings donated to them, unfortunately due to their size they needed some suitable footings designed.  Due to the lack of available funds to pay for engineering and installation, the basketball rings ended up lying on the ground, unusable.  When we heard about this, Operations Manager Sean Gibbs jumped into action and took some measurements and photographs of the rings and asked our Housing Civil Engineer Ben Lewis, to design a suitable footing system, free of charge!  A footing contractor then kindly volunteered his time one weekend and had it installed so that the kids can now use their brand new rings!

Thursday, 9 October 2014

Major Projects Won

East Grand Trunkway, Gillman
FMG Research House have been contracted by Bardavcol Pty Ltd to undertake a level 1 controlled fill for a industrial subdivision project at East Grand Trunkway Gillman, Stage 1 comprising 7 allotments which vary in size from approximately 9000m2 to 14000m2 and two access roads. Project value $12M.

Lindt, Sydney Business Park, Marsden Park

We have been engaged by design and construct builder Qanstruct to provide structural and civil engineering services for Lindt in Marsden Park. This project consists of a temperature controlled warehouse of approximately 20,000 square metres, including 20 metre cantilever awning, 5,400 square metres of maintenance area and chocolate production areas.
There is also a large 3 level office component of about 2500 sqm.
truck marshalling area, recessed truck docks and carpark for 320 cars on a site with a 5 metre fall that will add to the challenge for the civil design.

Yarraville Residential Development
FMG Engineering's environmental group has been engaged by a developer who has Council approval to construct apartments on a site that is contaminated and was historically used as a municipal landfill.  A condition of Council's approval is the completion of a rigorous soil and groundwater assessment and design of an engineered capping layer, under the supervision of an EPA appointed auditor.

Monash University C2 Residential Project
Monash University's new master plan for the Clayton Campus aims to increase the number of residential beds from the current 1,750 beds to 10,000. The first stage of the plan identified three sites to provide an extra 1,000 beds each. FMG have been engaged by architects McBride Charles Ryan as structural and civil engineers on one of the sites. The building is 7 stories high and has approx. 250 apartments over the top six levels. The ground floor is a retail area, with construction cost estimates at approximately $30 million.
The floors are post tensioned and are supported by internal and external precast panels. The internal and external panels are supported by columns at ground floor to allow for open spaces for the retail area. Whilst the façade is distinctive, it is only made up of precast panels of two different shapes.

Monash University

"Excellence in Multi-Stage Development" Norstar Steel Recyclers


Norstar has recently completed construction of a new shredder for their metal recycling plant. The client initially engaged Burns Hamilton to manage the design phase of the project that required management and co-ordination of the contractors and subcontractors involved in the project. This involved weekly design meetings to ensure that all information and drawings were sent to and coordinated with the relevant parties, and that all queries were answered as soon as possible to keep the project moving.

The client was so impressed with our design management that they engaged FMG Engineering to manage the construction stage.

Being responsive to the client, following up straight away and communicating regularly made a huge difference to the project. All consultants and contractors on the project benefited by being able to access information in a more timely manner, resulting in a smoothly run and highly successful project.

Michelle Collett          
Structural Engineer, VIC
 
Norstar Steel Recyclers

"Exceeding Expectations at Weston Milling"


An initial forensic inspection on a warehouse building identified a number of structural deficiencies including severe deterioration of parts of the building that required urgent rectification, primarily affecting their warehouse and distribution network.

The client's initial internal advice and estimates were suggesting an unacceptable timeframe for downtime of this critical business element.

FMG Engineering was engaged to investigate and facilitate an approach to drastically reduce the time the warehouse was under repair. From approval to proceed, design documentation was produced in a staged manner from three weeks with Development Approvals being gained for the initial stages within six weeks.

FMG Engineering facilitated a team to deliver methodology, design, documentation and construction of works with the warehouse being unavailable for only six months. We also assisted the client in securing temporary facilities for the duration of the works.

FMG Engineering's pro-active approach led to a rapid solution to a complex set of problems, far exceeding Weston Milling's expectations.

Serhan Halil
Senior Structural Engineer

Testimonial

"When MAURI anz needed to demolish and rebuild a stone warehouse in Adelaide, we asked FMG Engineering to provide structural engineering support to the project. From the outset, FMG Engineering gave great advice on everything from the initial emergency propping of the warehouse, to the complete rebuild of the facility. The outcome was a demolition and construction project that was finished to a high specification, on time, and to a very tight budget. FMG Engineering's involvement was much wider than structural engineering. I have no doubt that without their input we would not have got such good value for money for an activity, that as a food company, we rarely conduct. I would enlist FMG Engineering's support again in a heartbeat."

John Power
Operations Director
MAURI anz


Weston Milling Warehouse

New Boss Appointed at FMG Engineering - The Advertiser 7 October 2014

Adelaide based consulting firm FMG Engineering has appointed Matthew Loftes to the newly created role of chief executive after an exhaustive review of the company.

Formerly the company's chief operating officer, Mr Loftes will work alongside managing director Peter Bayetto to drive the company's growth and development.

"I initiated a warts-and-all client review which confirmed FMG's quality and integrity with a fine reputation developed over 40 years," he said.

"However it highlighted areas in which we can improve and this has become a priority. My emphasis will be to maintain our quality, integrity and to add value for our clients."

FMG has offices in Adelaide and Melbourne and shopfront premises in Tanunda and Mt Gambier. It employs about 150 engineers, scientists, technicians and support staff.

"We have bucked the economic trend with 50 percent annual revenue growth over the last two years, having merged with Burns Hamilton and Partners who have a strong background in commercial development," Mr Loftes said.

Matthew Loftes - Chief Executive Officer